Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place
17959124_web1_Coastal-GasLink-local-sections
Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

含羞草研究社淎t KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,含羞草研究社 the statement reads. 含羞草研究社淎reas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

含羞草研究社淎t KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance含羞草研究社

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

含羞草研究社淐oastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,含羞草研究社 said David Pfieffer, CGL president.

含羞草研究社淐oastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

含羞草研究社淚 have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

含羞草研究社淚 have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.含羞草研究社



editor@interior-news.com

Like us on and follow us on



Thom Barker

About the Author: Thom Barker

After graduating with a geology degree from Carleton University and taking a detour through the high tech business, Thom started his journalism career as a fact-checker for a magazine in Ottawa in 2002.
Read more



(or

含羞草研究社

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }