Vernon on hook for nearly $330,000 to fix railway crossing

City told by Transport Canada of number of issues, non-compliance with Anderson Way crossing
web1_240111-vms-anderson-railway-crossing_1
The City of Vernon has to spend nearly $330,000 to upgrade the railway crossing at Anderson Way. (Google Maps image)

The City of Vernon has its own cross to bear over a delinquent railway crossing.

Council voted unanimously Monday, Jan. 8, at its first regular meeting of 2024, to spend nearly $330,000 from 2022 uncommitted balance reserves to fix the railway crossing at Anderson Way, in the city含羞草研究社檚 north end.

The city was alerted by Transport Canada in September about a grocery list of concerns and non-compliance issues regarding the crossing.

含羞草研究社淎re we sure this is our responsibility for this issue, and are we ready to step up and pay to correct it?含羞草研究社 questioned Coun. Brian Guy.

Senior project manager Jackson Stewart assured Guy the city was partially to blame.

含羞草研究社淣ew Transport Canada grade crossing regulations were published in November 2014, and amended in 2019 and 2021,含羞草研究社 said Stewart. 含羞草研究社淭he regulations were updated to improve public safety at all grade crossings across Canada. When the crossing was installed, it was correct for the time.含羞草研究社

The letter received by the city also pointed out problems and non-compliances that are the responsibility of the railway, Canadian National. The city含羞草研究社檚 transportation department responded with a letter outlining the corrective actions it will take.

含羞草研究社淭o remedy these concerns and meet compliance, an upgraded crossing warning system must be installed,含羞草研究社 said Stewart.

Transport Canada said the deadline for compliance is Nov. 28, 2024.

Staff recommended the city provide a maximum of 50 per cent of the cost of the new system at the crossing, which would be $328,822. That number could drop if Canadian National is successful in its application for a Transport Canada Rail Safety Improvement Program grant, which would cover 50 per cent of the construction costs and would be shared between CN and the city.

Vernon含羞草研究社檚 portion, if the grant is received, would be $164, 411.

Council voted unanimously in favour of spending the money to fix the crossing.

READ MORE:

READ MORE:



Roger Knox

About the Author: Roger Knox

I am a journalist with more than 30 years of experience in the industry. I started my career in radio and have spent the last 21 years working with Black Press Media.
Read more



(or

含羞草研究社

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }